Fast-tracking a vote that was originally expected to happen two months from now, state utility regulators plan to decide ...
While the Louisiana Public Service Commission voted 4 to 1 in favor of Entergy moving forward with its plans to build tree ...
Entergy's Louisiana unit received the state's regulatory approval to move forward with infrastructure investments tied to ...
The Richland Parish data center project, first announced in 2024, is one of the largest private capital investments in ...
This approval facilitates enhancements to the state’s electric grid, benefiting customers and preparing for future energy ...
When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
If the Public Service Commission approves the plan, Entergy will have the greenlight to build three new gas plants to power ...
State utility regulators approved a plan Wednesday to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for a massive data center it’s building in ...
The facility is set to require more than double the energy needed to power the entire city of New Orleans during peak summer ...
The Louisiana Public Service Commission (LPSC) has given the go-ahead for the installation of three natural gas turbines set ...
Louisiana Public Service Commissioners voted four to one to approve Entergy’s three new gas plants to power Meta’s ...
The fast-tracked approval is drawing concern from advocates who say average ratepayers are at risk. Entergy and supporters of ...